Bournemouth, Dorset and Poole (Structural Changes) Order 2018 Work package
A work package focussed on the Bournemouth, Dorset and Poole (Structural Changes) Order 2018, made available on 29 March 2018, subject to the Draft affirmative procedure.
There are 17 business items actualising 22 steps.
Business items having happened - Business items having no dates
Business items having happened
-
28 March 2018
-
29 March 2018
-
16 April 2018
-
24 April 2018
-
25 April 2018
-
Considered by the Joint Committee on Statutory Instruments (JCSI) (House of Commons and House of Lords)
Instrument not drawn to the special attention of the Houses by the Joint Committee on Statutory Instruments (JCSI) (House of Commons and House of Lords)
-
Motion to approve the instrument tabled by the Government (House of Lords)
-
-
16 May 2018
-
21 May 2018
-
23 May 2018
-
Instrument approved (House of Commons)
-
Chamber debate (House of Lords)
-
Question on motion to approve the instrument put (House of Lords)
Instrument approved (House of Lords)
-
Instrument can be made (signed into law)
-
Procedure concluded in the House of Commons and the House of Lords (House of Commons and House of Lords)
-
-
25 May 2018